Project Background

This $1.5million project will improve the water service to the Tamworth Base Hospital, a critical customer, and the renew the road surface in Dean Street.

Timeline

  • Timeline item 1 - complete

    Johnston Street Water Main Early Works

    Starting Monday 8 February

  • Timeline item 2 - complete

    Water Main Replacement - Start of Works

    Work commencing Tuesday 16 February along Dean and Johnston streets.

    Works to take approx. 7 weeks

  • Timeline item 3 - complete

    Water Main Replacement

    Works restarted mid-June 2021

  • Timeline item 4 - complete

    Water Main Replacement - End of Works

    Expected to be completed late November.

  • Timeline item 5 - active

    Road Resurfacing

    Expected to start March 2022.

Road Access Changes

Through out this project there will be a range of impacts on users of Johnston and Dean Street.

There will be detours in place while works are taking place, and there may be occasions where residents will be unable to park out the front of their property. However, these changes will only be for a short time only.

When travelling on Johnston or Dean Street during this time please take extra care and pay attention to all traffic control directions in place.