Background Information

Council is investing $350,000 in sewer cleaning and CCTV investigation works as part of the Annual Renewal Program.

A Contractor has been engaged to carry out the works on 50km of sewer systems in Tamworth, Manilla and Barraba between mid-July and mid-November 2022.

These works are vital to the continuing operation and functionality of the sewer network in the region.

The works will cause very minimal disruption to businesses and residents, anyone affected will be communicated with directly by the Contractor.

Project Timeline

  • Timeline item 1 - complete

    Contractors arrive in Tamworth

    Mid-July 2022

  • Timeline item 2 - complete

    Cleaning and CCTV works are carried out

    Cleaning and CCTV works are carried out in Tamworth, Manilla and Barraba.

  • Timeline item 3 - complete

    Project completion

    The project is scheduled to be completed in November 2022.

Tamworth CCTV map

Manilla CCTV map

Barraba CCTV map